| COMPANY DETAILS | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Persons allocated to carry out task: (List all persons who will be working on site for the contractor at any time) |
Signature: (All persons working on site are required to read fully and sign SWMS). |
Duties and responsibilities: (List details of duties and responsibilities of specific personnel, eg, daily safety checks, maintenance checks, etc). |
Qualifications / Certificates of Competency / Training / Experience required to carry out task: (List details of qualifications, certificates, training and experience and needed to carry out the tasks required). |
||||||
|
|||||||||
|
|||||||||
| COMMENTS OR REVIEW | AMENDMENTS | ||||||||
|
|
||||||||
| Plant and equipment required: (List all plant and equipment to be used by contractor this for job). |
Safety and maintenance checks required: |
| Engineering details / Certificates/Approvals required: (Provide details required for work listed as hazardous or requiring specific work methods, eg, demolition, formwork, falsework, tilt slab construction, etc). |
Legislation / Standards / Codes of Practice applicable: (Ensure that work methods comply with or exceed legislated requirements or applicable Codes of Practice, and that the relevant Codes, etc, are available on site). |
|
|||||||
| COMPILATION OF SWMS | |||||||
| STEP | |||||||
| ACTIVITY | |||||||
| HAZARDS | |||||||
| RISK (1) | |||||||
| RISK CONTROLS | |||||||
| RISK (2) | |||||||
| BY WHOM | |||||||
| RISK LEVEL MATRIX | |||||||||||||||||||||||||||||||||||||
|
|
||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||
| STEP | ACTIVITY | HAZARD(S) | RISK (1) | RISK CONTROL(S) | RISK (2) | BY WHOM |
| 1 | Security of site and public safety | Personal injury to workers on site, members of the public | L4 | Erect signs warning of ammonia discharge Inform staff that oil draining will be carried out | L6 | Tech |
| 2 | Ammonia detection activated by ammonia smell | Nuisance evacuation and emergency services call | L | Disable local ammonia detection in this area Ensure ventilation fan is operating | L6 | Tech |
| 3 | Location of oil drain point | Location may present egress and ingress problems | L3 | Ensure adequate escape route Ensure self closing valve is fitted | L | Tech Site supervisor |
| 4 | Opening hand valves | Escape of ammonia/oil under pressure | L2 | Ensure all valves etc are in good condition Trained and experienced personnel only to carry out this work | L6 | Tech Site supervisor |
| 5 | Draining of oil | Escape of ammonia/oil under pressure | M3 | Ensure pressure in vessel is acceptable for oil draining Use self closing “Deadman “ valve for draining oil Open valve slowly | L6 | Tech |
| 6 | Draining of oil | Burns from liquid ammonia | M2 | PPE, safety glasses, gloves, protective clothing | L5 | Tech |
| 7 | Uncontrolled ammonia discharge | Evacuation of site, injury to personnel via burns and asphyxiation | M2 | Ensure all on site staff are aware of emergency procedure Ensure MA staff are trained in emergency procedures | M2 | Site supervisor MA supervisor |
| 8 | Minor leaks from drain valves | Minor irritation to workers, | L5 | Ensure that caps are fitted once oil draining complete and no ammonia/oil present in valves or pipe work | L6 |